Marine Construction & Engineering

Jetty

Project Details

Project:
Dun Laoghaire Rathdown Baths Project

Client:
SIAC-Manovani JV

Works:
Construction of new jetty

Date:
August 2018-October 2019

Description

The works consisted of:

  • Preparation and clearance of foreshore including area below low water mark
  • Underwater rock breaking and removal of rock to depth of 3m
  • Installation of foundation works using bespoke screed frame
  • Placement, fixing and infill of 5t concrete caissons for construction of jetty walls
  • Design & fabrication of customised steel shutter for construction of in-situ outer wall
  • Construction and finishing works to outer jetty wall
  • Placement of rock armour for revetment formation and toe protection, upon completion of new jetty

Marine Specialists Equipment

  • 36t 360° long reach excavator
  • 50t 360° standard reach excavator
  • Dive control unit
  • Screed Frame
  • Bespoke shutter units
  • MEWP