Marine Waste Water Outfall Pipe & Diffuser Installation

belmullet-1

Project Details

Project:
Belmullet Sewerage Scheme

Client:
Roadbridge

Works:
I
nstallation of 622m of outfall pipe

Date:
June/July 2017

Description

The works consisted of:

  • Excavation of the trench
  • Installation approximately 622m of 250mm Ø plastic pipe
  • Supply of ballast weights (concrete collars)
  • Installation of ballast weights on outfall pipe
  • Preparation of diffuser bed with Reno Mattresses
  • Installation of stainless steel diffuser in 4m of water 420m below MHWS
  • Connection of the outfall pipe to the diffuser
  • Backfill and profiling of excavation

Marine Specialists Equipment

  • Komatsu 360PC LR 10 360° excavator
  • 6No CP4084 pontoons
  • 2No 16.5m Spud Legs
  • Mini Tug vessel – Marine Bravo
  • Barge based Dive Spread

Notes

The outfall and diffuser were located in Mullet/Blacksod Bay Complex SAC (site code 000470). Consequently, all relevant pollution control and biosecurity procedures and protocols were implemented and adhered to for the duration of the works.